Bay du Nord
Newfoundland and Labrador’s next offshore oil project, in plain English. Every item links to its source.
Where it is
About 500 km out, in the Flemish Pass. The fields producing today sit on the shallow Grand Banks. Bay du Nord is past the edge of the banks, in about 1,100 m of water.
- Producing field
- Bay du Nord, in development
- Every 100 km from St. John's
- Sea floor at 200 m, the edge of the Grand Banks, then 1,000, 2,000 and 3,000 m
Coastline and depths: Natural Earth (opens in a new tab). Field locations: Hibernia (opens in a new tab), White Rose (opens in a new tab), Hebron (opens in a new tab), Terra Nova (opens in a new tab), Bay du Nord (opens in a new tab). Distances are straight-line.
From discovery to first oil
The milestones so far, and what's expected next.
-
2013
Discovered
Statoil, now Equinor, and Husky announce a "high impact" oil find about 500 km northeast of St. John's, in about 1,100 m of water.
Source: CBC News (opens in a new tab)
-
April 2022
Federal approval
Ottawa approves the project after its environmental assessment.
-
May 2023
Put on hold
Equinor delays the project by up to three years over rising costs.
Source: World Oil (opens in a new tab)
-
March 2026
Benefits deal signed
The province and Equinor agree on local work, including fabrication in NL and a fund for the Bull Arm dry dock.
Source: Government of Newfoundland and Labrador (opens in a new tab)
-
April 2026
Design contracts awarded
BW Offshore gets the floating production vessel design; Subsea Integration Alliance gets the subsea work.
-
July to October 2026
New partner lineup
BP sells its share to Equinor, then Shell agrees to take 30%. Equinor stays the operator.
-
November 2026
Development plan approved
The offshore regulator approves the development plan, and the federal and provincial energy ministers sign off.
Source: C-NLOER (opens in a new tab)
-
Early 2027Expected
Final investment decision
The go or no-go on building it. Equinor says it is on track for early 2027.
-
2031Expected
First oil
When production is expected to start, as reported in October 2026.
Latest Bay du Nord news
Newest first.
-
Regulator and both governments approve the Bay du Nord development plan
The offshore regulator, C-NLOER, approved Equinor's development plan and updated benefits plan for Bay du Nord, with conditions set out in its decision report. The federal and provincial energy ministers have both signed off, which clears the last major regulatory step. Equinor and partner Shell still have to make the final investment decision, and offshore work would need further permits from the regulator.
Source: C-NLOER (opens in a new tab)
-
Province says it plans to take a 10% stake in Bay du Nord
The premier told reporters the province intends to take a 10% equity stake in the project, but it isn't guaranteed. Once the project is sanctioned, the province will have 90 days to decide, and the cost of the stake is still being worked out. A final investment decision is expected in the first quarter of 2027.
Source: VOCM (opens in a new tab)
-
Equinor's supplier list grows to 30 packages
Equinor's Bay du Nord procurement page now lists 30 expressions of interest for suppliers. The newest is for audio-visual systems installation and support. Most of the others are equipment: pumps, heat exchangers, pressure vessels, instruments and valves.
Source: Equinor (opens in a new tab)
-
Equinor keeps Bay du Nord on track for an early 2027 decision
Equinor's chief financial officer told investors the company isn't changing its plans ahead of a final investment decision early next year. The project is estimated at about $14 billion, with first oil expected in 2031. The provincial government is considering a stake of up to 10%.
-
Shell agrees to take 30% of Bay du Nord
Equinor agreed to sell a 30% interest to Shell and keeps 70% as operator. The field sits about 500 km offshore in the Flemish Pass, and phase one is expected to recover over 400 million barrels.
-
Design contracts go to BW Offshore and Subsea Integration Alliance
Equinor awarded front-end engineering and design contracts. Subsea Integration Alliance takes the subsea layout, cables and flowlines. BW Offshore is designing the floating production vessel it will also supply, and has opened an office in St. John's.
-
Province and Equinor sign the Bay du Nord benefits deal
The agreement counts over 31 million hours of work over 25 years, including at least 3 million hours of fabrication. At least 95% of subsea fabrication is to be done in the province, with a $200 million fund for a floating dry dock at Bull Arm and 100 jobs at an onshore operations centre.
Source: Government of Newfoundland and Labrador (opens in a new tab)
The rest of the offshore industry
The producing fields, exploration, contracts and the companies that supply them.
-
Shell, Equinor and OilCo bid over $260 million for offshore exploration licences
The offshore regulator, C-NLOER, announced bids on 10 exploration parcels, the first bids in several years. Shell won six parcels with $210.6 million in work commitments, Shell and Equinor together won two more for $30 million, and the province's oil company, OilCo, put reserve bids of $20 million on the last two.
Source: Government of Newfoundland and Labrador (opens in a new tab)
-
First West White Rose well is drilled
Cenovus said in its third-quarter results that drilling of the first well at the West White Rose platform is finished, and work to complete the well and tie it in is underway. Cenovus's production from its Atlantic region averaged about 14,000 barrels a day in the quarter, down from 15,000 in the second quarter.
-
Suncor selling its Terra Nova and White Rose stakes to Ithaca Energy
Suncor agreed to sell its 48% of Terra Nova, 40% of White Rose and 38.6% of West White Rose to Ithaca Energy, a North Sea operator, for $1.2 billion plus up to $350 million more depending on oil prices. Ithaca plans to take over as operator of Terra Nova and takes on a $500 million well compliance program there starting in 2027. The sale is expected to close in early 2027, and Suncor keeps its shares of Hibernia and Hebron.
Questions people ask
What is Bay du Nord?
An offshore oil project about 500 km northeast of St. John's, in the Flemish Pass, in about 1,100 m of water. Equinor is the operator, and phase one is expected to recover over 400 million barrels.
When will Bay du Nord start producing oil?
Equinor expects to make its final investment decision in early 2027, with first oil expected in 2031, as reported in October 2026.
Who owns Bay du Nord?
Equinor operates it. BP sold its 37.2% share to Equinor in July 2026, and in October 2026 Equinor agreed to sell 30% to Shell and keep 70%. The provincial government is considering a stake of up to 10%.
How many jobs will Bay du Nord create?
The benefits deal signed in March 2026 counts over 31 million hours of work over 25 years, including at least 3 million hours of fabrication in the province and 100 jobs at an onshore operations centre.
How far offshore is Bay du Nord?
About 500 km from St. John's, past the edge of the Grand Banks. The fields producing today, Hibernia, Hebron, Terra Nova and White Rose, are 315 to 350 km out.